Samsung SDS breaks ground on Gumi AI data center: 60MW initially, up to 120MW, ₩427.3 billion investment, completion by end-2028 (report)

Announced November 2, 2026

Verified (fact)

Samsung SDS held a groundbreaking ceremony on the 2nd for its Gumi AI data center on a site of about 14,000 pyeong (roughly 46,000 square meters) in Gongdan-dong, Gumi, North Gyeongsang Province, South Korea. Initial power capacity is 60MW, expandable in stages up to 120MW depending on demand, with ₩427.3 billion invested and completion scheduled for the end of 2028. It targets enterprise AI services and demand for robot training and automation at manufacturing sites, and was presented as the first visible result of Samsung's roughly ₩60 trillion physical AI cluster investment in Korea's Yeongnam region announced in July.

Why it matters (interpretation)

The first large-scale case in Korea of attaching GPU infrastructure for robot training to a domestic manufacturing hub.

Confidence medium · official source pending

Sources

More about Samsung SDS